Maintenance works at FASoS

This summer, maintenance works will take place around the FASoS buildings. The works are expected to last over the summer and will cause some noise nuisance. For an overview of the works to be carried out, please read below.

If you have any questions please contact Vincent Cordewener

  • The roof of GG76 will be replaced. The works will start Monday 17 June and are expected to last until Friday 5 July. There will be noise nuisance from the works but it is expected to be limited.
  • Paintwork GG90-92; the outside window frames of GG90-92 streetside, side façade (B-wing on the side of the corridor ) and the back (on the side of the garden) will be re-painted. Works will start 20 June and are expected to last for a few weeks depending on the weather.
  • Replacing of the floor in the Turnzaal; from 10 July until 19 July the floor of the Turnzaal will be replaced.

 

Submit your comment

Please enter your name

Your name is required

Please enter a valid email address

An email address is required

Please enter your message

FASoS Weekly © 2019 All Rights Reserved

Designed by WPSHOWER

Powered by WordPress